UMMC TRAFFIC FLOW UPGRADE
 Update on: 8/3/2017
 

UMMC INFO: 
Dear Valued Customer,

Please be informed that our premise will be going for some major renovations to upgrade our traffic flow due to the traffic density in our premise. The works will be done in stages as follows:

Section 1 : Road Widening & South Tower Frontage (13/2/2017-15/4/2017)

Section 2 : Taxi Stand (13/2/2017-12/8/2017)

Section 3 : Walkway@Existing Bustop (13/2/2017-22/4/2017

Section 4 : New Plaza: 1/4/2017-22/1/2018

Total construction period will take approximately 12 months and expected to finish in January 2018.

While the construction works are on, there will be a temporary closure to certain walkways and some traffic diversions mainly at the main entrance of our Main Tower, South Tower as well as our Emergency Building. Notices will be put up in stages in the affected areas.

Please also take note that our current food outlets located at the Emergency Building will be temporarily closed for renovations for approximately 6 months (expected from June 2017-December 2017). To accommodate our customers and staffs, we are trying to place a few food trucks and food kiosks in certain places.

As we try to accommodate everyone in every single plan, do expect some inconveniences throughout the construction period. Your patience is much appreciated and your cooporation and understanding is needed for us to deliver a better service for you in the future.



ADDRESS

  • Pusat Perubatan Universiti Malaya,
    Lembah Pantai, 59100,
    Kuala Lumpur, MALAYSIA

EMAIL

  • Email : ummc@ummc.edu.my

TEL

  • Phone No : 03-79494422
    Fax : 03-79492030

WEBSITE

  • WEBSITE : www.ummc.edu.my